Optimalisasi kinerja tim proyek dengan memanfaatkan metode CPM dan PERT dalam pekerjaan pematangan lahan
Main Article Content
Abstract
This study aims to conduct a study on optimizing work performance on the work team for
land development projects at PT PANARUB INDUSTRY in Brebes, Central Java, using
the CPM and PERT methods. Significant delays in project completion become the basis
for testing all project activities starting from planning through work breakdown
structures, determining duration, interrelationships between activities and conducting
standard deviation tests using a normal distribution table to determine the probability of
project completion by crashing which is the responsibility of full responsibility of the
project implementation team led by the Project Manager. The results of the three
scheduling studies, namely scheduling according to the initial time of the project duration
planning according to the CPM and PERT methods can cut work time significantly so that
it has an impact on the work performance of the project team. The CPM and PERT
methods really help the project team's performance, especially in accelerating the
optimization of time and cost efficiency, and the actions taken are based on accurate
calculations.
Article Details
References
Artika, Dian. Penerapan Metode Lean Project Management Dalam Proyek Konstruksi Pada
Pembangunan Gedung Dprd Kabupaten Ogan Ilir. Jurnal Teknik Sipil dan Lingkungan Vol. 2,
No. 1, Maret 2014.
Christiansen, Bryan and Harish C. Chandan. Handbook of Research on Organizational Culture and
Diversity in the Modern Workforce. Hershey PA, USA;IGI Global;2017.
A Guide to The Project Management Body of Knowledge. Sixth edition. Pennsylvania 19073-3299
USA;Project Management Institute, Inc.;2017.
Noe, Raymond A. et al. (2016). Fundamentals of Human Resource Management. Sixth Edition. 2 Penn
Plaza, New York, NY 10121;McGraw-Hill Education;2016:43
Wahyuni, Elvi dan Bambang Heriawan. Analisis Kinerja Proyek “Y” Menggunakan Metode Earned
Value Management (Studi Kasus Di Pt Asian Sealand Engineering). Journal of Applied
Business Administration Vol 2, No 1, Maret 2018;60-78;e-ISSN:2548990;2018.
Yuya Takakura, Tomoyuki Yajima, Yoshiaki Kawajiri, and Susumu Hashizume. Application of Critical
Path Method to Stochasticprocesses With Historical Operation Data. Chemical Engineering
Research and Design 1 4 9 ( 2 0 1 9 ) 195–208. Elsevier;2019.
Wiji Yuwono, M. Elfan Kaukab, Yusqi Mahfud. Kajian Metode PERT-CPM dan Pemanfaatannya
dalam Manajemen Waktu dan Biaya Pelaksanaan Proyek. Journal of Economic, Management,
Accounting and Technology (JEMATech) Vol. 4, No. 2, Agustus 2021. p-ISSN:2622-8394|eISSN:2622-8122. DOI:https://doi.org/10.32500/jematech.v4i2.1925.
Shanmugasundaram, S dan V. Mathan Khumar. Application of Project Scheduling and Cost analysis
Using PERT and CPM. International Journal of in Multidisciplinary and Academic Research
(SSIJMAR). Vol. 4, No. 2, April 2015;(ISSN: 2278-5973);pp:2-3.
Gurau, M. A.dan L. V. Melnic. An overview of critical path applied to project management with
WinQSB software. International Journal of Mathematical Models and Methods in Applied
Sciences. Issue 7, Volume 6;2012;pp:829-835.
Heizer J. dan Barry Render. Operation Management: Sustainability and Supply Chain Management.
th edition. New Jersey ;Pearson;2021:101
Agyei, Wallace. Project Planning And Scheduling Using PERT And CPM Techniques With Linear
Programming: Case Study. International Journal of Sscientific & Technology Research.
Georges N., Nabil Semaan, dan Joe Rizk. Crash: An Automated Tool for Schedule Crashing.
International Journal of Science, Environment and Technology. Vol. 3, No 2. ISSN: 2278-3687.
:375-377.
Desi Yasri. Pengaruh Overtime Terhadap Analisa Time Cost Trade Off Pada Proyek Pembangunan
Gudang Arsip Dan Perlengkapan Pekanbar. Jurnal Teknik Sipil Siklus, Vol. 4, No. 1, April 2018.